If you've bought a plug-in solar kit — or you're about to — there's one piece of paperwork that trips people up more than anything else: the G98 notification. It sounds bureaucratic, but it's genuinely one of the simplest parts of the whole process once you know what you're doing.

This guide walks through exactly what G98 is, whether it applies to your system, and the four steps to get it submitted — start to finish, in about 15 to 20 minutes.

The short version

G98 is a notification, not an application. You install your kit, switch it on, then tell your local network operator within 28 days. There's no fee, no approval to wait for, and no visit required for a standard 800W plug-in system.

What G98 actually is

G98 is short for Engineering Recommendation G98, published by the Energy Networks Association (ENA). It's the technical standard that governs how small generators — including plug-in solar kits — connect to the UK's local electricity network.

Any generator up to 3.68kW on a single-phase supply falls under G98, which covers every domestic plug-in solar kit on the market (all currently capped at 800W). The rule is often summarised as "connect and notify" — unlike its bigger sibling G99 (for larger systems), you don't need permission before you switch on.

Do you actually need to do this?

Yes, if your system is connected to the mains grid — even via a compliant hardwired connection to your consumer unit rather than a wall socket. G98 notification is a legal requirement, not an optional courtesy to your network operator. It applies whether you've had an electrician wire it in, or you're connecting a certified plug-in product under UKSI 2026/848 once that route opens on 27 August 2026.

⚠️
What happens if you skip it

Missing the 28-day window doesn't usually cause immediate problems, but it can create complications later — with a buildings insurance claim, a smart meter reading that doesn't match your usage pattern, or when your solicitor does searches during a house sale. It's a five-minute form that's much easier to do now than to backfill later.

Step 1: Find your DNO

Your DNO (Distribution Network Operator) is the company that physically owns and maintains the electricity cables in your area — this is not the same company as your energy supplier (the one that sends you a bill). You could be with Octopus or British Gas for your supply, while a completely different company owns the local wires.

The quickest way to find yours is the Energy Networks Association's postcode checker at energynetworks.org, or check your electricity bill — your network operator is sometimes listed there as "distributor" or "network operator." As a general guide, UK electricity distribution is split between a small number of regional operators, including UK Power Networks, National Grid Electricity Distribution, SP Energy Networks, SSEN (Scottish and Southern Electricity Networks), Electricity North West, and Northern Powergrid — but always confirm with the postcode checker rather than assuming based on region, since coverage areas don't map neatly onto county lines.

Step 2: Gather what you'll need

Have these ready before you start the form — it turns a fiddly process into a five-minute one:

📐
The most common mistake

People enter the solar panel wattage (e.g. 900W of panels) instead of the micro-inverter's registered AC output capacity (e.g. 800W). The DNO cares about what can actually be pushed onto their network, which is set by the inverter, not the panels feeding it.

Step 3: Submit the notification online

Go to your DNO's website
Search "[your DNO name] G98 notification" or look for a section called "connect generation" or "small-scale generation" — most DNOs now run this as an online form rather than a downloadable PDF.
Fill in the customer and installation details
Name, installation address, postcode, and contact details. This part is usually the most straightforward, since it's just confirming who and where.
Enter your equipment details
MPAN, inverter make/model, and AC output capacity. If your inverter is on the ENA's type-tested register, some forms let you select it from a dropdown rather than typing it manually.
Submit and save your confirmation
You'll typically get an on-screen or emailed confirmation, sometimes with a reference number. Save this — it's worth having on file for insurance, a future house sale, or if any query comes up later.

What happens after you submit

For a standard sub-3.68kW system, most DNOs simply log the notification on their network records — you won't receive a formal "approval" document, just confirmation that it's been received. Occasionally, a DNO may follow up with additional questions if a lot of small generators are already registered on the same local network segment, but this is rare for a single 800W system and doesn't mean you've done anything wrong.

💷
This isn't the same as getting paid for exported power

G98 notification just registers your generator on the network — it doesn't automatically enrol you in the Smart Export Guarantee (SEG), which pays you for electricity you export. SEG requires separate certification (typically MCS or an equivalent scheme) and a supplier-side export tariff.

G98 vs G99: which applies to you

For virtually every reader of this site, the answer is G98 — but here's the full comparison so you know why:

FactorG98G99
Applies to≤3.68kW single-phaseAbove 3.68kW, or 3-phase
ProcessNotify after connectingApply and wait for approval
Prior approval needed?NoYes
Typical timescaleSubmit within 28 days4–12 weeks before install
Relevant to plug-in solar?Yes — all current kitsNo, unless stacking well beyond 800W

Common mistakes to avoid

Choosing a kit with G98 already sorted

One upside of buying an established plug-in solar brand: the inverter is already on the ENA's type-tested register, so this whole process is friction-free. These are the same kits we recommend elsewhere on the site, and all three are pre-cleared for G98:

⭐ Best Overall — UK Government Partner

EcoFlow STREAM Balcony Solar System 800W

~£449
Saves up to £115/year — pays for itself in ~4 years

Two 450W panels, 860W micro-inverter with Wi-Fi and app monitoring. Already listed on the ENA type-tested register, so your G98 form is a straightforward dropdown selection.

Check Price on Amazon →
💰 Best Value — Fastest Payback

Hoymiles HMS-800-2T Micro-Inverter Kit

~£180
Under 4-year payback — best ROI on the market

The DIY installer's favourite, and a long-standing entry on the G98 register. 12-year warranty, dual MPPT inputs, 97%+ efficiency.

Check Price on Amazon →
📋
Not sure plug-in solar is even legal for your situation yet?

Start with our full explainer on current UK rules and what's changing in 2026 before you buy.

🔋
Adding a battery? Same G98 process applies

Battery-equipped kits like the EcoFlow STREAM or Anker SOLIX Solarbank 2 still notify under G98 as a single combined unit. See our battery storage guide for the full comparison.

Summary — the key facts

Once it's submitted and confirmed, you're done — there's nothing to renew, and no ongoing paperwork unless you move house and need to re-notify the new property's DNO.

Frequently Asked Questions

Do I need to notify my DNO for plug-in solar?

Yes. Any generator connected to the UK grid, including an 800W plug-in solar kit, falls under Engineering Recommendation G98 and must be notified to your local Distribution Network Operator (DNO) within 28 days of the system being switched on.

Is G98 notification free?

Yes, submitting a G98 notification is free and typically takes 10 to 20 minutes online once you have your MPAN and inverter details ready.

What's the difference between G98 and G99?

G98 covers single-phase generators up to 3.68kW, which includes all domestic plug-in solar kits, and only requires notification after connection. G99 applies above that threshold and requires the DNO's approval before you install, which can take several weeks.

What happens if I don't notify my DNO?

Missing the notification window can create complications later with buildings insurance claims, smart meter readings, or when selling your property, since there is a record mismatch between what's connected and what the network operator knows about.